Roosevelt and Pinehurst Way NE Paving & Safety Project
Updated July 25, 2025
What's Happening Now?
Please join us for a community open house from 5:30pm – 7:00pm on Wednesday, August 13th at Hazel Wolf Elementary School, where the project team will share the project’s early design (currently at the 30 percent milestone) and hear your feedback.
Note this event is a ‘drop-in ‘open house and there is no formal presentation. Stop by anytime from 5:30pm – 7:00pm! Hope to see you there!
Additionally, if you are a business owner along the project route and currently use an existing load zone, we invite you to take a brief 3–4 minute online survey. Your input will help us better understand how load zones are used and guide potential changes as part of this project.
Project Overview
We are repaving Roosevelt Way NE and Pinehurst Way NE between NE 92nd St and 15th Ave NE to extend the life of the roadway by 10 to 20 years. Along with resurfacing the asphalt, we will be making important infrastructure upgrades, such as fixing the road base, installing curb ramps that meet ADA (Americans with Disabilities Act) standards, and improving drainage systems.
In addition to restoring the infrastructure, the project will also look for ways to improve facilities for different types of transportation, in line with the Complete Streets policy. Proposed upgrades include new crosswalks, protected bike lanes, and bus stop improvements, such as shelters and lighting. These changes aim to make the area safer and more accessible for all.
Project Background
As part of Seattle’s ongoing pavement preservation strategy, this project focuses on maintaining critical infrastructure while integrating safety improvements. The roadway has experienced wear and tear, impacting vehicle, pedestrian, and bicycle travel. By resurfacing and repairing the road, we aim to prevent further damage and lower long-term maintenance costs.
The project builds on previous improvements at the Pinehurst Way NE and NE 117th St intersection, enhancing mobility for residents and improving access to Hazel Wolf K-8 School. By addressing safety and connectivity along this corridor, SDOT is working to meet the goals outlined in the Seattle Transportation Plan (STP) and Vision Zero Action Plan.
Project Area
Project Schedule
Design began in winter 2024 and is scheduled for completion in spring of 2026. Construction is scheduled to begin in 2027.
Funding
The project is partially funded by an $8.7 million Federal Highway Administration grant.
Materials
30% Design Proposed Changes vs. Existing Conditions