Safe Routes to School: Wing Luke Elementary
Updated March 25, 2024
What's Happening Now?
Major work for the Kenyon Way S Sidewalk project is complete! We are finishing a few small tasks and you may see crews and/or equipment in the area.
We are excited to announce that we are starting construction on an extension of the Wing Luke Elementary Neighborhood Greenway northward as soon as spring 2024! (See the new project map below.) We will be installing the Neighborhood Greenway in stages, starting this spring and finishing in 2024.
Improvements will occur at the following locations 1) S Holly Park Dr from S Myrtle Pl to 40th Ave S, 2) 39th Ave S from S Holly Park Dr to S Kenyon St, 3) 40th Ave S between S Holly Park Dr and S Holden St, and 4) S Holden St between 40th Ave S and 39th Ave S.
Project Overview
The Neighborhood Greenway extension has been planned in coordination with the earlier project already funded through the Safe Routes to School and Urban Trails and Bikeways programs and will further enhance safe travel to Wing Luke Elementary for children and families and make it easier to walk and bike in the neighborhood. Safe Routes to School is a national movement to make it easier and safer for students to walk and bike to school.
Current Work
The New Neighborhood Greenway routing will include the following street improvements:
- Speed humps or cushions to calm traffic
- Upgrades at the intersection of S Myrtle Pl and S Holly Park Dr including a bike crosswalk, turning boxes, and other bike facilities
- Stop signs with stop bars on side streets intersecting the Neighborhood Greenway
- Tree trimming and sidewalk smoothing
- Wayfinding signs and markings
Project Area Map
Completed work
S Kenyon St and 37th Ave S
We prioritized this location to fill a gap in the sidewalk and urban trail network, enabling kids and families to walk safely to Wing Luke Elementary School. Project elements completed include:
- a new sidewalk
- a midblock raised crosswalk on S Kenyon St, and
- a new connection to Chief Sealth Trail
Near Wing Luke Elementary, a new sidewalk and curb ramp are complete.
S Kenyon St at Wolcott Ave S and 52nd Ave S
We made improvements along S Kenyon St at 52nd Ave S and at Wolcott Ave S. It was a continuation of work that began in 2019 with new planting strips and sidewalks. Project elements completed include curb ramp and drainage improvements, as well as upgraded sidewalks.
New curb ramps and upgraded sidewalks at S Kenyon St near the intersections of 52nd Ave S and Wolcott Ave S.
Funding
This project was funded by the 9-year Levy to Move Seattle, which was approved by voters in 2015, as well as the local Safe Routes to School program.
Materials
- Neighborhood Greenway Extension Mailer, February 2024
- Kenyon Way S Sidewalk and Student Art Celebration Event flyer, June 2023
- Kenyon Way S Construction Detour Flyer, February 2023
- Kenyon Way S Pre-Construction Flyer, December 2022
- Kenyon Way S Final Traffic Circulation Flyer, June 2022
- Kenyon Way S Final Design Postcard Mailer, April 2022
- Wolcott Ave S project map, June 2020
- 37th Ave S and S Kenyon St (Wing Luke Elementary) project map, June 2020
Translation & Interpretation
If you need this information translated, please call (206) 684-0392.
如果您需要把下列資訊翻譯成中文,請致電 (206) 684-0392.
Si usted necesita esta información traducida al español por favor llame al (206) 684-0392.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt, xin gọi số (206) 684-0392.
Kung kailangan ninyong isalin sa Tagalog ang impormasyong ito, paki-tawag lang sa (206) 684-0392.