Admiral Way North and South Bridges Seismic Retrofit
Updated April 3, 2025
What's Happening Now?
We’re making progress on retrofits that will help the Admiral Way North and South Bridges better withstand earthquakes.
Here’s What Crews Are Working On:
- Concrete repairs on damaged sections of the bridge.
- Wrapping parts of the bridge in carbon fiber to make it stronger.
- Painting piers and setting up scaffolding to prepare for retrofits under the deck.
Photo caption: Crews paint bridge piers as part of the Admiral Way North and South Bridges Seismic Retrofit Project, March 2025.
Traffic Reminders
Admiral Way SW (on top of the bridge)
- Both sidewalks are open for people walking, biking, and using mobility devices.
- The work zone will change from time to time over the next several months, but we’re keeping at least one lane of Admiral Way SW open in each direction.
Fairmount Ave SW Closure Reminder (below the bridge)
- Fairmount Ave SW under the bridge is closed to all travelers during construction. This closure keeps everyone safe while work happens on the bridge above, and helps our crews work efficiently.
We’ll continue to share updates as construction moves forward. If you have questions, please contact us at BridgeSeismicRetrofit@seattle.gov. You can also sign up to join our project listserv and receive project updates.
Project Overview
Earthquakes could have a major impact on Seattle’s infrastructure. To address these seismic risks, the City of Seattle established a bridge seismic program to assess how vulnerable the City’s bridges were to earthquakes, and to retrofit bridges to better withstand the potential impacts of an earthquake.
As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the Admiral Way North and South Bridges. The Admiral Way North and South Bridges are older bridges built prior to modernizing the seismic design code.
The bridges are on SW Admiral Way between 39th Ave SW and Walnut Ave SW, above Fairmont Ave SW. While it seems like one bridge when you’re traveling on it, the Admiral Way North and South Bridges are actually two bridges, side-by-side. Both will be retrofitted, making them stronger and safer in the event of an earthquake.
The photo above shows an aerial view of the SW Admiral Way Bridge and surrounding streets, showing its connection to nearby residential areas.
We're not changing the current use and operation of the bridge. The Admiral Way North and South Bridges seismic retrofit will strengthen existing bridge components and reduce the bridge’s vulnerability to earthquakes. Major construction work includes:
- Installing carbon fiber wrapping to strengthen certain bridge elements
- Slope stabilization
- Steel painting
- Replacing bridge gusset plates
- Repairing cracks and damaged concrete
- Replacing the expansion joints at both ends of the bridge
Project Area
The bridges are on SW Admiral Way between 39th Ave SW and Walnut Ave SW, above Fairmont Ave SW.
What to expect during construction
Construction began July 2024 and is anticipated to be complete Summer 2025.
To complete the work as safely and efficiently as possible, there will be lane and sidewalk closures on SW Admiral Way at the bridge throughout construction. Additionally, Fairmount Ave SW under the bridge will be closed to people walking, biking, rolling, and driving during construction. We understand these closures will impact everyone who uses the bridge and Fairmount Ave SW regularly and we will do what we can to minimize impacts.
We currently anticipate the following construction impacts:
- Lane reductions on SW Admiral Way at the bridge.
- A full closure of Fairmount Ave SW during construction.
- Work in the public right-of-way near your home or business.
- Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance.
- Staged construction equipment and materials as well as noise, dust, and vibrations in the work area.
- Typical weekday work hours of 7 AM – 5 PM, Monday through Friday.
Project Schedule
Construction schedules are subject to change and depend on factors such as weather and availability of crews and materials.
Funding
The project is funded through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city. In addition, this project has received federal funding.
Get Involved
We’re committed to keeping you informed and collaborating with neighbors to minimize construction impacts as much as possible. Here’s how you can stay updated on the project:
- Sign up for our project listserv to receive weekly project updates
- Email the project team at BridgeSeismicRetrofit@seattle.gov
- Leave a voicemail at (206) 775-8734. A project representative will return your call.
Project Materials
- Admiral Way Fact Sheet (2024)
Translation and interpretation
- If you need this information translated, please call (206) 775-8734.
- 如果您需要此信息翻譯成中文 請致電 (206) 775-8734.
- Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 775-8734.
- Si necesita traducir esta información al español, llame al (206) 775-8734.
- Odeeffannoon kun akka siif (206) 775-8734.
- Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 775-8734.
- የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ (206) 775-8734.
- ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 775-8734.
- 당신이 번역이 정보를 필요로하는 경우에, (206) 775-8734? 전화 해주십시오.