West Seattle Golf Clubhouse Restroom Renovation
Updated: April 21, 2025
Spring 2025
Planning and design are underway for the proposed project with a goal milestone of having concepts for the public to view by the end of summer 2025. The project is on schedule to go to bid in March 2026.
The restrooms will be closed during construction, but portable restrooms will be available during this time.
Location
West Seattle Golf Course Clubhouse, 4470 35th Ave SW, Seattle, WA 98126
Budget
$1,000,000
Schedule
Planning and Design: Spring 2025 - Spring 2026
Construction: Winter 2026
Completion: Spring 2027
Project Description
Seattle Parks and Recreation (SPR) has identified the need to renovate the clubhouse restrooms at West Seattle Golf Course (WSGC). The existing restrooms are original to the building (1961) and are undersized for current user needs and do not meet accessibility requirements. Aside from the restrooms, neither the parking nor the entrance to the clubhouse is compliant with accessibility standards. The outdated condition, inefficient layout, and lack of accessibility to the facility reduce programming, events, and user needs.
The proposed scope of work aims to renovate the parking stalls, entrance ramps, ingress/egress doors, and restrooms to create an inclusive, accessible, and sustainable facility at WSGC that better serves the community, including thousands of annual golf patrons and banquet hall attendees. The restrooms will be redesigned to accommodate all genders, consistent with the best practices outlined in the 2016 Seattle Parks and Recreation All Gender Restrooms / Changing Room Study. The facilities will also incorporate sustainable building practices and environmentally responsible materials. These renovations aim not only to meet current accessibility codes but to anticipate future needs, ensuring longevity and adaptability.