Dahl Playfield Restroom Renovation
Updated: June 15, 2026
Summer 2026
Seattle Parks and Recreation (SPR) identified the Dahl Playfield Restrooms in 2023 as a renovation project. The restroom caught fire during the design development phase and now requires additional work to address the fire incident. The project scope now includes a structural repair, roof and electrical replacement, and removing accessibility barriers.
The restrooms will remain closed through design and construction. Construction activity may impact the play area, more information will be available as we near construction.
Location
Dahl Playfield, 7700 25th Ave. NE, Seattle, WA 98115
Budget
Seattle Parks and Recreation provides $1.78 million for planning, design, and construction.
Schedule
Design & Permitting: July 2026
Bidding: July-August 2026
Construction: Fall 2026 - Spring 2027
Completion: Summer 2027