Walt Hundley Playfield Synthetic Turf Replacement

Updated: February 8, 2026

Winter 2026

Seattle Parks and Recreation (SPR) is in the early design phase of replacing the synthetic turf at Walt Hundley Playfield. A design consultant has been selected to develop site plans and assist with progressing the project through construction.

Location

Walt Hundley Playfield 6920 34th Ave SW, Seattle, WA 98126

Budget

The total budget for this project is $1,883,986 in funding provided by Seattle Metropolitan Park District (MPD).

Schedule

Planning: Winter 2025 - Fall 2025
Design & Permitting: Winter 2026 – Winter 2027
Construction: Summer 2027 
Completion: Fall 2027

Project Description

Per Seattle Parks and Recreation’s asset lifecycle policy for synthetic turf replacement, this project will replace the synthetic turf at Walt Hundley Playfield and address athletic field access barriers.

Walt Hundley Playfield will be closed during construction. SPR will work with our design team and athletic scheduling team to limit the impact on field users.

Parks and Recreation

Michele Finnegan, Interim Superintendent
Mailing Address: 100 Dexter Ave N, Seattle, WA, 98109
Phone: (206) 684-4075
Fax: (206) 615-1813
pks_info@seattle.gov

Sign Up for Latest Updates

Subscribe

Healthy People, Thriving Environment, Vibrant Community