Walt Hundley Playfield Synthetic Turf Replacement
Updated: February 8, 2026
Winter 2026
Seattle Parks and Recreation (SPR) is in the early design phase of replacing the synthetic turf at Walt Hundley Playfield. A design consultant has been selected to develop site plans and assist with progressing the project through construction.
Location
Walt Hundley Playfield 6920 34th Ave SW, Seattle, WA 98126
Budget
The total budget for this project is $1,883,986 in funding provided by Seattle Metropolitan Park District (MPD).
Schedule
Planning: Winter 2025 - Fall 2025
Design & Permitting: Winter 2026 – Winter 2027
Construction: Summer 2027
Completion: Fall 2027
Project Description
Per Seattle Parks and Recreation’s asset lifecycle policy for synthetic turf replacement, this project will replace the synthetic turf at Walt Hundley Playfield and address athletic field access barriers.
Walt Hundley Playfield will be closed during construction. SPR will work with our design team and athletic scheduling team to limit the impact on field users.