Updated: October 27, 2025
Winter 2025
Seattle Parks and Recreation (SPR) has issued the Notice to Proceed (NTP) to Kessel & Associates for construction on a three-play-area renovation package, beginning Monday, July 28, 2025. This package includes play area improvements at Ward Springs Play Area, Bryant Neighborhood Park Play Area, and View Ridge Playfield Play Area, with phased construction planned to minimize community disruption.
Construction is underway at View Ridge and Ward Springs; these two sites will run concurrently and are expected to be completed by the end of 2025. To take advantage of favorable weather, the contractor is partially mobilized at Bryant. The Bryant play area remains open while the View Ridge play area is closed.
View the final play equipment renderings below!
We received many comments about adding restrooms. We’ve forwarded the comments for SPR asset planning’s consideration; however, at this time, the project is not able to address restroom needs.
Location
Bryant Neighborhood Playground: 4103 NE 65th St, Seattle 98115
Budget
Seattle Park District provides $1,098,000 for planning, design, and construction.
Schedule
Planning: 2023
Design: 2024 - Spring 2025
Construction: Late Fall 2025 - Early 2026
This project is part of a package of three play areas that are being renovated. The above planned construction duration includes renovations at all three locations.
Project Description
This project will replace the existing play area and make accessibility improvements. All improvements will meet accessibility requirements.
The play area will be closed throughout construction.
Community Participation
Thank you to everyone who joined us during the community engagement phase. We value your feedback and participation. Please follow this page for construction and completion updates.
Public Meeting - 4/10/24
Open House - 10/18/23