Southwest Seattle Fiberoptic Cable Installations

Map showing location of fiberoptic cable installation

Map showing location of fiberoptic cable installation

Project Description

Seattle City Light crews will be replacing overhead fiberoptic cables between several utility substations in the southwest Seattle area. This work is needed to provide reliable communications between City Light's electrical substations and operations network.

Location

Southwest Seattle

What's Happening Now?

Project Update (June 2022): Crews have one day of work between the South and Delridge substations, which will require a clearance on the energized lines and additional coordination with other parties. The remaining Delridge to Duwamish substation work is 60% complete. This portion will be completed by the end of the year.

Community Benefits

  • This work is needed to provide reliable communications between City Light's electrical substations and operations network.

Anticipated Impacts

  • Crews will be replacing overhead fiberoptic cables between several substations in the southwest Seattle area. The planned cable routes will run between the following City Light facilities:
    • South Substation to Delridge Substation
    • Delridge Substation to Duwamish Substation
  • Customers can expect temporary parking, sidewalk and traffic restrictions during this project. Flaggers will direct traffic through the work zone.
  • Some noise is expected from construction activities.
  • Maintenance power outages are not expected. If outages are needed, customers will be notified in advance.
  • During this project, City Light will have the opportunity to upgrade infrastructure and replace utility poles that are in poor condition.
  • The project will require rolling slowdowns on State Route (SR) 99 and SR 509. Details about this phase of work will be shared with customers once a construction schedule has been determined.

  • Construction Start: Mid-July 2020
  • Daily Work Schedule: Mon-Fri: 7 a.m.-5 p.m., Sat/Sun: 8 a.m.-5 p.m. 

Hien Trinh
Project Manager
(206) 459-8259
hien.trinh@seattle.gov

City Light

Debra Smith, General Manager and CEO
Address: 700 5th Ave, Seattle, WA, 98104
Mailing Address: PO Box 34023, Seattle, WA, 98124-4023
Phone: (206) 684-3000
SCL_ExternalComms@seattle.gov

Seattle City Light was created by the citizens of Seattle in 1902 to provide affordable, reliable, and environmentally responsible electric power to the City of Seattle and neighboring suburbs.