Project Description
We are upgrading the underground electrical infrastructure in the Brace Point area to provide a more resilient and reliable power system. This project will replace aging conduits, cables, vaults, and streetlights, reducing the risk of unexpected outages and improving service for residents.
Location

Construction will take place in the Endolyne/Brace Point area.
What's Happening Now?
Project Update (October 2026): Underground civil construction is approximately 66% complete. Our crews have installed 7,848 linear feet of conduit and 20 underground electrical vaults. We expect to finish most civil construction activities by spring 2027. We know this is a later timeline than initially communicated, and we appreciate your continued patience as crews complete this important work.
Customers can sign up to receive monthly email construction updates at bit.ly/scl-bracepoint.
Community Benefits
This project is an investment in the future of the Brace Point community. Replacing aging electrical infrastructure, will significantly improve power reliability and reduce the risk of unplanned outages. Upgraded street lighting will enhance visibility and safety, creating a more secure environment for pedestrians and drivers alike.
Additionally, we are working closely with the Seattle Department of Transportation (SDOT) Urban Forestry group to protect and preserve trees in the area. Once construction is complete, all affected streets, sidewalks, and landscaping will be restored to meet City of Seattle standards, maintaining the character and accessibility of your neighborhood.
Anticipated Impacts
- Trenching and Excavation: Work will occur mainly in the public right-of-way, including streets, lawns, and planting strips. Property rights will be obtained where work is needed in private property.
- Traffic and Parking Disruptions: Temporary road closures and detours will be in place during work hours (exact hours to be determined). Driveway access near construction areas may be limited during work hours, with advance notice provided to affected residents.
- Temporary Surface Covers: Trenches will be covered with steel plates outside of work hours to maintain safety and accessibility.
- Planned Power Outages: Scheduled outages will be necessary to complete the work safely. We will notify affected residents in advance.
- Mail and Waste Collection: There will be no disruptions to mail delivery or garbage, recycling, and yard waste services. Please continue placing bins at the curb as usual.
- Private Property Impact: Crews will replace infrastructure up to the electrical vault where private service lines connect. They will not replace private service connections. Customers are not required to upgrade their underground service connection as part of this project. However, customers may decide to upgrade their property’s electrical service at any time. Please review our electrical service guidance for more information.
- Tree Protection and Restoration: We will work closely with SDOT’s Urban Forestry group to minimize tree impacts and mitigate removals when necessary.
- Street and Landscape Restoration: After construction, all affected streets, sidewalks, and landscaping will be fully restored and repaved according to SDOT standards.
Schedule
Construction Start: On private property on Aug. 18, 2025. Crews will move to the public right-of-way in early September.
Estimated Completion: We expect to finish most civil construction activities by spring 2027. We know this is a later timeline than initially communicated, and we appreciate your continued patience as crews complete this important work. As civil construction finishes, our electrical crews will pull in new cables. We will publish an updated electrical work timeline soon.
Daily Work Schedule: Monday - Friday, 7 AM - 5:30 PM
