Brace Point Underground Cable Replacement

City Light Undergrounding Project

Map showing construction work area in the Brace Point neighborhood

Project Description

Seattle City Light is upgrading the underground electrical infrastructure in the Brace Point area to provide a more resilient and reliable power system. This project will replace aging conduits, cables, vaults, and streetlights, reducing the risk of unexpected outages and improving service for residents.

Location

Construction will take place in the Endolyne/Brace Point area.

What's Happening Now?

Project Update (April 2025): The construction plan is complete, and we are accepting construction contractor applications, or “bids,” through April 23. Then, we will evaluate the bids and sign an agreement with a contractor. We anticipate construction to start in July 2025. The anticipated schedule includes the following dates:

  • March 26, 2025 - Advertise for bid
  • April 23, 2025 - City Light bid review
  • July 2025 - Anticipated start of construction
  • September 2026 - Anticipated project completion

Community Benefits

This project is an investment in the future of the Brace Point community. Replacing aging electrical infrastructure, will significantly improve power reliability and reduce the risk of unplanned outages. Upgraded street lighting will enhance visibility and safety, creating a more secure environment for pedestrians and drivers alike.

Additionally, we are working closely with SDOT’s Urban Forestry group to protect and preserve trees in the area. Once construction is complete, all affected streets, sidewalks, and landscaping will be restored to meet City of Seattle standards, maintaining the character and accessibility of your neighborhood.

Anticipated Impacts

  • Trenching and Excavation: Work will occur mainly in the public right-of-way, including streets, lawns, and planting strips. Property rights will be obtained where work is needed in private property.
  • Traffic and Parking Disruptions: Temporary road closures and detours will be in place during work hours (exact hours to be determined). Driveway access near construction areas may be limited during work hours, with advance notice provided to affected residents.
  • Temporary Surface Covers: Trenches will be covered with steel plates outside of work hours to maintain safety and accessibility.
  • Planned Power Outages: Scheduled outages will be necessary to complete the work safely. City Light will notify affected residents in advance.
  • Mail and Waste Collection: There will be no disruptions to mail delivery or garbage, recycling, and yard waste services. Please continue placing bins at the curb as usual.
  • Private Property Impact: Private service connections to homes are not included in this project. Homeowners may need to submit a service request to Seattle City Light to install or upgrade their service as a result of this project.
  • Tree Protection and Restoration: Seattle City Light will work closely with SDOT’s Urban Forestry group to minimize tree impacts and mitigate removals when necessary.
  • Street and Landscape Restoration: After construction, all affected streets, sidewalks, and landscaping will be fully restored and repaved according to SDOT standards.

Schedule

Construction Start: July 2025

Estimated Completion: September 2026

Daily Work Schedule: To be determined.

City Light

Dawn Lindell, General Manager and CEO
Address: 700 5th Ave, Seattle, WA, 98104
Mailing Address: PO Box 34023, Seattle, WA, 98124-4023
Phone: (206) 684-3000
SCL_ExternalComms@seattle.gov

Seattle City Light was created by the citizens of Seattle in 1902 to provide affordable, reliable, and environmentally responsible electric power to the City of Seattle and neighboring suburbs.