Lake City Healthy Streets

Cedar Park & Olympic Hills

Updated May 30, 2024

What's Happening Now?

As soon as this week you may see some pavement markings and signs going up as our crew prepares to start constructing the permanent installments for the Cedar Park Healthy Street!

We will install permanent signage with a concrete block base and newly painted curb space around it at each intersection along the Healthy Street. Along with installing typical Healthy Street features, we will also be adding all-way stops to the two intersections at 37th Ave NE and NE 135th St. Unauthorized on-street parking located within 20 feet of the intersection will be removed for the permanent sign installation.

At intersections where neighbors requested planters, we will install the permanent signage with a planter sign base. And, as soon as the installation is complete, we will reach out to those neighbors about holding a plant pickup event.

For more information about the plans for this permanent Healthy Street, please view "Design Elements" (see below).

As we previously announced, the installation of features on the Olympic Hills Healthy Street will be paused until late Summer. Our crews have some time and funding to complete maintenance on several blocks of streets in the area. They will be putting down a new asphalt treatment—it's called a slurry seal—and it needs a little bit of time to set and dry before we come in and add Healthy Street pavement markings and other additions.

What to expect during construction:
Typical construction hours are weekdays, 7 AM to 5 PM, and may include weekend work. Other expected construction effects may include:

  • Noise and vibration
  • Dust and debris
  • Construction staging and parking impacts near the work sites
  • “No Parking” areas and other parking impacts
  • Crosswalk and sidewalk closures, with detours for people walking and biking
  • Roadway closures and detours for vehicle traffic

Please note that the construction schedule may change due to unforeseen circumstances (i.e., weather, soil conditions, etc.). We encourage you to sign up for email updates to get the most updated information on construction. We encourage you to sign up for email updates to get the most updated information on construction.

Example of Permanent Healthy Street sign base and planter

Example of permanent Healthy Street signs and planter. 

Project MapMap that shows Olympic Hills, Cedar Park Healthy Streets, and Greenways, and Little Brook Healthy Street

Click to view a larger map.

Design Elements

Cedar Park

Along with installing typical Healthy Street features on the Cedar Park Healthy Street, we will also be adding all-way stops to the two intersections at 37th Ave NE and NE 135th St: 

Cedar Park Design Map

Materials

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.