South Cloverdale Street between Martin Luther King Jr. Way South and Renton Avenue South: Construction Update 7/13/2009 Work is scheduled to begin on Monday, July 20th, depending on weather. There will be parking restrictions along the project boundaries as needed. The contractor will put up no parking signs on the affected block(s) 3 days before construction begins on that block This project will ensure complete pedestrian access on either side of this section of S Cloverdale St by filling in the gaps between the existing sidewalks. Travel lane width will not be changed. Trees will be included.
|
|