30th Avenue SW Sidewalk Improvements
Construction Update
7/20/2009: This project is substantially complete. Seattle City Light will be moving the utility poles in the next few months. Once that is complete, SDOT will return to replace the asphalt patch in the sidewalk with concrete.
5/05/09: Demolition is complete and concrete pouring has begun. The project is on schedule for completion in early June. |
The Seattle Department of Transportation’s contractor plans to begin construction of 30th Avenue SW sidewalk improvements on Monday, April 6. The sidewalk will be constructed on the eastern side of 30th Avenue SW from SW Brandon Street to the existing sidewalk at the top of the hill (just north of SW Juneau Street and High Point). Some surveying work will start the week prior and no parking signs will be placed three days before construction begins.
The construction is expected to take five to six weeks, depending on the weather. For the duration of construction, 30th Avenue SW between SW Findlay and Brandon Streets will be closed to through traffic. A detour route will be signed for through traffic to use 29th Avenue SW.
Parking will be restricted in the area under construction. Access to driveways will be maintained.